Update VCF and SDDC componets .

 

Update VCF and SDDC Components.


Procedure:


1.Navigate to Inventory and Click on Workload Domain.

2.First MGMT domain need to update. Click On MGMT Domain.

  



3.Once you will Click on MGMT domain, it will show you different options like summary, services, update/patches, update history, host, cluster security.




Summary: You will be able to see version details of all components like VCF, vCenter, NSX and Hosts.

Hosts: Once you will click on Hosts Tab you will be able to see all assigned hosts in domains.

Cluster: In Cluster details you will be able to see all cluster running in domain.

Security: Once you will click on security tab then you will be able to see certificate details for all components.

Update and patches: when you click on Update and patches, you will be able to see Pre-check option in right side.

4.First click on Pre-check, Once pre-check will be green for all components you are good to proceed with update VCF and other components.

 



5. You will be able to see schedule update /update click on update. After that it will start updating VCF to target version.

 


6.Once VCF will be updated to target version you can update the other components as per VCF upgrade sequence in similar fashion.

7.It will populate the next components update option.

Thank You .